In this section, you will learn how to:
Controlling the shades involves regulating their brightness and colour temperature for optimal visibility and ambience. Configuring manual overrides for pre-defined light settings allows you to further improve energy efficiency and user comfort. Adaptive lighting settings also help enhance productivity and reduce operational costs.
Configuring Shade Controls
- In the Main Menu, under Admin Options, in the Controls subsection, click Shades.
The Shade Controls page is displayed. - In the Select Floor field, select the floor for which you want to set the shade controls.
The corresponding shades floor plan showing the centroids of each shade zone is displayed. - In the Quick Control field, if required, select a tag to filter shades by the tag associated with the shade.
- In the Search field, search for the specific shade you are looking for.
- In the right pane, click Show/Hide Shades and then select Show Actual Zone or Hide Actual Zone to see or hide the entire shade zone area.
You can also hover your mouse over a shade zone to see the details.Note: For the floor plan to display the different shade zones, they must have been configured using the Drawing Tool feature.
- To select a shade zone, click the select element icon
and then click the shade zone you want to control.
A blue dotted rectangle is displayed around the selected shade zone.
OR
In the left pane, under Control, select the required shade zone. You can select as many shade zones at a time as required. - To define the controls:
- For a single shade zone, right-click on the zone area and then click Control Shade Manually.
The control window is displayed with option to set the shade level. - For multiple zones, select the shade zones in the left pane and then click Control.
The control window is displayed with option to define the shade level.
Note: The control window will display the option to define the shade level only if it has been enabled in the Shade profile associated with the shade.
- For a single shade zone, right-click on the zone area and then click Control Shade Manually.
- Slide the shade up or down to set the shade level or enter a value between 0 and 100, where 0 stands for fully closed shades and 100 stands for fully open shades.
Note: If you have selected multiple shades, then the shade level selected in the Control window will apply to all selected shades for the selected dates and time.
- If scenes are configured, select the required Scene to be applied to the Shade.
Note: Scenes will be displayed in the control window only if they have been configured for a shade. For details on adding a shade scene, click here.
Managing Shade Schedule
This feature allows you to customize different shade schedules for different days of the week and for different areas in your office building. You can also configure different schedules for different times within a day for the same area.
To create a shade schedule:
- In the Main Menu, under Admin Options, in the Controls subsection, click Shade Schedule.
The Shade Schedule page is displayed with the calendar for the current week showing the existing shade schedules, of any. You can click the right and left arrows to see the schedules of the previous and next week. - To add a new schedule, click New Schedule.
- Enter or select the required field information.
Field Description Name*
Enter a name for the shade schedule.
Date Range*
Select the date range for which the shade schedule should be applicable.
Start Time*
Select the time at which the shade schedule should be in effect.
Repeat On Days
Select the days on which this shade schedule should repeat.
Active
Select this checkbox to make this shade schedule active.
Quick Control
Select tags for spaces where you want to apply the shade schedule. For example, select Meeting Room.
Select location
Select the location where this shade schedule would be applicable.
The shades in the selected location are displayed in the right pane. - Select at least one shade from all the available shades at the selected location.
- Click Set Control.
The Controls window displays controls applicable for the shade(s). - Slide the shade up or down to set the shade level or enter a value between 0 and 100, where 0 stands for fully closed shades and 100 stands for fully open shades.
Note: If you have selected multiple shades, then the shade level selected in the Controls window will apply to all selected shades for the selected dates and time.
- Click Apply.
The shade schedule is saved and is added to the Shade Schedule calendar.Note: To deactivate a shade schedule, select the schedule from the calendar, deselect the Active checkbox and click Set Control.